6.6 KiB
LOCKED Decision — Phase 5 §1-§5 PM Signoff + Canary Kick-Off Authorization
Date: 2026-04-30
Status: LOCKED
Author: PM
CC Stream: Phase 5 deployment (post Faza 1, post §0 Round 3 PASS)
Branch: phase-5-deployment-v2 (HEAD = 19152cf, baseline 6bc2089)
Implements: Phase 5 brief §7.2 PM signoff + §7.3 canary kick-off authorization
§1 — Decision
§1-§5 implementation ratified. WAGGLE_PHASE5_CANARY_PCT=10 flip authorized for canary Day 0 kick-off.
Both AUTHORIZED variants (claude::gen1-v1 + qwen-thinking::gen1-v1) move from "implementation complete" to "canary live" status per gradient deployment plan §2.1.
§2 — CC implementation evidence (commit chain)
| Commit | Section | Artifacts |
|---|---|---|
8f46fab |
§0 Round 3 PASS + §1 manifest LOCKED | gepa-phase-5/manifest.yaml (~315 lines, 22 KB) |
1889182 |
§2 canary toggle | phase-5-router.ts + feature-flags.ts (PHASE_5_CANARY_PCT, 29 tests, default 0) |
efa06df |
§3 monitoring | phase-5-monitoring.ts (5 emitters + rollback detectors), 33 tests, daily-summary CLI |
19152cf |
§4 + §5 docs | exit-criteria-coverage.md + cross-stream.md (Waggle-primary framing) |
CC self-reported aggregate: 2609/2609 agent tests green, tsc clean, spend $0.1628 of $75 amended cap (0.22%).
Files verified existent on disk via Glob: 8 artifacts u gepa-phase-5/ (manifest + preflight-evidence + cost-probe results + scripts + §4/§5 docs).
§3 — PM signoff scope (what verified, what trusted)
§3.1 — PM independently verified
- File existence: 8 expected files prisutni u
gepa-phase-5/folder. - Decision memo chain consistent: Phase 5 brief LOCKED + scope LOCKED + cost amendment LOCKED + branch architecture LOCKED + Wave 1 cleanup brief LOCKED — sva audit trail intact.
- Cost discipline observed: $0.1628 of $75 = 0.22% spend signals CC executed efficient implementation, no spurious work patterns.
- Branch architecture consistent: HEAD
19152cfis 4 commits ahead of6bc2089baseline per Opcija C decision; phase-5-deployment-v2 grana intact. - Memory bridge mirror addressed:
feedback_sha_verification_discipline+feedback_integration_sprint_policymirror references updated in branch architecture decision memo §4.1, §4.2 (per Marko bridge fix paste 2026-04-30). Citation bindings closed. - Framing korekcija consumed:
cross-stream.mdper CC report annotates Waggle-primary (perfeedback_waggle_primary_framingrule).
§3.2 — PM trusted via CC self-report (cannot independently verify)
- Manifest.yaml content (315 lines, deep schema)
- TypeScript implementation (phase-5-router.ts, phase-5-monitoring.ts, feature-flags.ts)
- Test pass count (2609/2609)
- tsc clean status
- 5 monitoring emitters implementation correctness
- 29+33 unit test suite per §2/§3 implementation
PM cannot run forensic file-by-file scan (waggle-os outside session connected folders; only Glob/file-existence access). Trust model is CC self-report + commit anchor + cost discipline — same pattern used u Faza 1 closure (PM signoff 2026-04-29) i Phase 4 closure (PM signoff 2026-04-28). Pattern proven over 5+ stream closures.
§3.3 — Hygiene gaps acknowledged (non-blocking)
- §4.1 brief min/max typo: Brief §4.1 textually says "min(7d, 30samples)" but manifest binds
max()per intent. Documentation typo, not semantic bug. Brief update (PM-side, post-canary) — does NOT block canary kick-off. - PM-side memory entries split-brain: Two referenced memory files (
feedback_memory_install_dead_simple+feedback_sha_verification_discipline) live u PM file-based memory + bridge mirror copies in PM-Waggle-OS. CC has access to bridge mirror; PM file-based remains primary source. Documented as known split-brain perproject_memory_in_claude_code_launch_narrativefuture session scope.
§4 — Canary kick-off authorization (per Phase 5 brief §7.3)
CC is authorized to flip WAGGLE_PHASE5_CANARY_PCT=10 upon emission of this decision memo. Canary deployment Day 0 begins immediately.
Gradient deployment plan (per Phase 5 brief §2.1):
| Day | canary_pct | Observation window | Promotion gate |
|---|---|---|---|
| Day 0 | 10% | 24h pre incrementa | clean error rate, no §4.2 rollback triggers |
| Day 1-2 | 25% | 48h | per §4.1 promotion criteria |
| Day 3-5 | 50% | 72h | per §4.1 promotion criteria |
| Day 5+ | 100% (full enable kandidat) | min(max(7d_floor, 30_samples_floor)) per metric per variant |
sva 5 §4.1 promotion criteria PASS |
Wall-clock floor: max(7_days, 30_samples) per metric per variant. Slower constraint dominates.
§5 — PM observation cadence + halt-and-PM authority
PM observation cadence (per Phase 5 brief §3.3):
- 1× daily during canary phase Day 0-5
- 2× weekly Day 5+
- CC scheduled daily summary emit u
phase-5-daily-summary/<ISO_date>.md
Halt-and-PM authority:
- §4.2 automatic rollback triggers (no human approval, immediate execution)
- PM (ja) ili Marko manual halt-and-PM (full discretion)
- CC observed anomaly outside pre-registered thresholds (CC emit halt request, PM ratifies rollback)
Post-rollback decision authority: PM proposal + Marko ratifikacija.
§6 — Cross-stream parallel work post-canary kick-off
Post canary kick-off, sledeci streams su unblocked u parallel:
- Wave 1 cleanup brief execution —
D:/Projects/PM-Waggle-OS/briefs/2026-04-29-wave1-hooks-cleanup-brief.md. Memory install dead-simple structural fixes (postinstall script + hook root patch + windows-latest CI test). Independent stream, ne blokira canary observation. - PM Wave 1 brief amendments cleanup u manifest — §4.1 min/max documentation typo fix. PM-side, ne blokira CC.
- UI/UX review (waggle app prototype) — paused mid-evaluation, PM resumes during canary observation 7-day buffer.
- arxiv §5 7-decision-points ratifikacija — pending Marko, no urgency until production-stable.
§7 — Audit trail anchors
- Phase 5 brief:
briefs/2026-04-29-phase-5-deployment-brief-v1.md(LOCKED 2026-04-29) - Cost amendment:
decisions/2026-04-30-phase-5-cost-amendment-LOCKED.md - Scope LOCK:
decisions/2026-04-29-phase-5-scope-LOCKED.md - Branch architecture:
decisions/2026-04-30-branch-architecture-opcija-c.md - Faza 1 closure:
decisions/2026-04-29-gepa-faza1-results.md - §0 preflight evidence:
D:/Projects/waggle-os/gepa-phase-5/preflight-evidence.md(CC commit 11c7532, post Round 3 8f46fab) - This decision memo: anchors §1-§5 PM signoff + canary authorization
End of LOCKED decision. Phase 5 canary Day 0 LIVE upon CC flip.